Stop Portland Waste Incinerator v Secretary of State for Housing, Communities and Local Government, Powerfuel Portland Limited & Dorset Council [2025] EWHC 777 (Admin)

On 2 April 2025, Mrs Justice Lang dismissed a statutory challenge to the Secretary of State’s grant of planning permission for an energy recovery facility at Portland Port in Dorset. The case (AC-2024-LON-003475) concerned the interpretation and application of the 2019 Bournemouth, Christchurch, Poole and Dorset Waste Plan and the adequacy of the reasons given for approval.

Background and legal issues

The proposed facility would process up to 202,000 tonnes of non-hazardous residual waste each year. Dorset Council refused permission in March 2023, but the Secretary of State recovered the appeal and allowed it on 16 September 2024 following a public inquiry.

The claimant applied for statutory review under section 288 of the Town and Country Planning Act 1990. Ground 1 concerned policy interpretation, rationality and adequacy of reasons. Grounds 2 and 3 concerned asserted factual errors in the comparison with Canford and the interpretation of the alternative-site requirement.

Interpreting the waste plan

At paragraphs 75 to 90 the judge explained that the spatial strategy was not confined to locating facilities close to the principal source of waste. It also pursued sufficient capacity, the waste hierarchy and self-sufficiency. The plan contemplated strategic facilities serving the entire plan area and flexibility where allocated sites did not come forward.

The court applied the distinction between interpreting policy and exercising planning judgment explained in Tesco Stores Ltd v Dundee City Council [2012] UKSC 13. The Inspector and Secretary of State were entitled to evaluate the relevant policy objectives together rather than treat proximity as automatically decisive.

Alternative sites and evidence

At paragraphs 140 to 147 the court rejected the argument that Policy 4(a) required an abstract comparison with every allocated site or their cumulative potential. The relevant comparison was with available allocated sites capable of meeting the need in question. Actual development proposals were relevant to assessing availability and capability.

The court also rejected the renewed application for permission on Ground 2, concerning information about the Canford proposal. On the facts of that decision, the Green Belt constraint was decisive; the asserted changes were not sufficient to alter the outcome.

Disposition and practical implications

At paragraph 148 permission to apply for statutory review was refused on Grounds 2 and 3 and the substantive claim on Ground 1 was dismissed. A subsequent appeal confined to adequacy of reasons under Policy 4(c) was dismissed by the Court of Appeal on 6 November 2025, [2025] EWCA Civ 1405.

For practitioners, the decision illustrates why comparisons with allocations must address actual availability and capability, and why a decision letter should be read in the context of the policy as a whole. It does not establish that any later facility at Canford must be refused or that proximity is irrelevant.

The judgment is Crown copyright under the Open Justice Licence.

The complete judgment is available to Gold members below.

Important legal note: Planning Geek is a planning consultancy, not a law firm. This page provides general planning information and is not legal advice. Case law must be read in its factual and legal context and may be affected by later judgments, legislation or policy. Where the original judgment is available, it remains the authoritative source. If the outcome matters to a live case or dispute, take advice from an appropriately qualified planning solicitor or barrister.

Copyright and licensing: Crown copyright and other rights in judgments and source material remain with the relevant rights holders. Where a judgment is reproduced from Find Case Law, it is used under the Open Justice Licence and the source should be acknowledged. Material obtained from other sources is reproduced only where the applicable terms permit it. Planning Geek does not claim copyright in the text of court judgments.

Affected by this case, or spotted something we should check? Report an issue with this page