Winters v Secretary of State for Communities and Local Government and another [2017] EWHC 357 (Admin)

The point in plain English: prior approval cannot retrospectively authorise development already begun. Winters concerned a proposed house extension, but its interpretation of the permitted development regime has particular significance for developers tempted to start works before obtaining the necessary prior approval.

On 24 February 2017, Mr John Howell QC, sitting as a Deputy High Court Judge in the Planning Court, dismissed Suzanne Winters’ application under section 288 of the Town and Country Planning Act 1990. The application challenged a Planning Inspector’s decision concerning a larger home extension at Hornchurch in the London Borough of Havering.

Important legal note: Planning Geek is a planning consultancy, not a law firm. This page provides general planning information and is not legal advice. Case law must be read in its factual and legal context and may be affected by later judgments, legislation or policy. Where the original judgment is available, it remains the authoritative source. If the outcome matters to a live case or dispute, take advice from an appropriately qualified planning solicitor or barrister.

Copyright and licensing: Crown copyright and other rights in judgments and source material remain with the relevant rights holders. Where a judgment is reproduced from Find Case Law, it is used under the Open Justice Licence and the source should be acknowledged. Material obtained from other sources is reproduced only where the applicable terms permit it. Planning Geek does not claim copyright in the text of court judgments.

What happened in Winters?

Ms Winters sought prior approval for a six-metre rear extension under Part 1 Class A of the Town and Country Planning (General Permitted Development) (England) Order 2015 (GPDO). Havering refused prior approval on adjoining-occupier amenity grounds. The notice was received after the relevant 42-day period, an issue on which the applicant relied in her appeal.

During the Inspector’s site visit, however, foundations and brick walls appeared to have been constructed in the approximate position of the proposed extension. The applicant argued that these works were instead repairs to a patio and retaining structure. Having invited responses from both parties and examined building-control records and photographs, the Inspector concluded that building work on the proposed extension had already begun.

The Inspector dismissed the appeal notwithstanding the council’s late notification. Ms Winters challenged the decision in the High Court, arguing that the prior approval application could still be determined, that the expired period was decisive and that the Inspector had made an unlawful finding about commencement.

Why prior approval cannot follow commencement

The court distinguished the permission granted by the GPDO from the procedural conditions that must be satisfied before it can be relied upon. The application and decision under paragraph A.4 concerned a proposed development. The required information had to be given to the authority before development started, and the prior approval process related to the whole proposal rather than whatever work happened to remain unfinished.

At paragraph 30 the court held that an application under the relevant condition could not be made in respect of development already begun. Partially completed works did not become eligible simply because a developer subsequently submitted plans and waited for an answer. The court also rejected the suggestion that this imposed a penalty. The normal route, where a proposal did not meet the GPDO conditions, was a planning application, potentially including an application covering works already carried out under section 73A.

That is a timing rule, not a blanket prohibition on pursuing permission for the same physical development. The distinction matters when assessing whether to submit a prior approval application, an ordinary planning application or a lawful development certificate.

What about a council missing the deadline?

The court accepted that the procedural 42-day mechanism could allow qualifying development to proceed where the council had not notified its decision on time. But it could not retrospectively validate part of a development already commenced in breach of the requirement to apply first. The Inspector was therefore not obliged to allow the appeal merely because the authority had responded too late.

In other words, a deadline matters only where the underlying proposed works satisfy the applicable permitted development scheme. A developer cannot use the expiry of the decision period to cure earlier non-compliance with the relevant GPDO conditions.

The Inspector’s fact-finding was upheld

The judge also considered whether the Inspector had investigated adequately what was being built. The decision-maker had raised the point, invited the parties’ evidence and assessed the differing accounts against what he observed on site. The High Court found that this was a permissible inquiry and that the Inspector had not acted irrationally.

The applicant also suggested that a material factual error had occurred over the position and depth of the works. However, the Inspector had not been clearly challenged about the measurement when the point was raised, and the court did not find a qualifying material error of fact. The section 288 challenge was dismissed.

How the judgment is used in later planning decisions

Winters was decided under the larger-home-extension prior approval procedure in Part 1 Class A. It was not itself a Class MA office-to-residential conversion case. Nevertheless, its reasoning on commencement has been cited in later decisions where a GPDO prior approval right likewise requires the developer to obtain approval or wait for the relevant statutory period before starting.

For example, an Inspector expressly relied on Winters when dismissing a Class MA appeal at Ormskirk on 4 November 2026 after finding that the internal conversion had been completed and the property occupied. See Planning Geek’s Class MA guide for the separate conditions that apply to conversions from Use Class E to Class C3.

The related judgment in RSBS Developments [2020] EWHC 3077 (Admin) addresses a different timing problem: the effect of unlawful building works on permitted development eligibility and why later remedial action does not retrospectively authorise the earlier change of use.

Complete original judgment

The complete 15-page approved High Court judgment was delivered by Mr John Howell QC, sitting as a Deputy High Court Judge, on 24 February 2017, case CO/941/2016. The judgment confirms that the relevant larger-home-extension prior approval application could not retrospectively authorise development already begun, and it dismisses the section 288 challenge.