Councillors have backed the Como Street redevelopment in Romford, which would replace a public car park with 138 homes without an initial affordable housing allocation.
According to local reports, Havering’s Strategic Planning Committee voted five to zero on 26 November 2026 to support the application from council-owned Mercury Land Holdings.
The scheme includes 135 flats and three houses, with the tallest apartment block reaching nine storeys alongside lower buildings.
The vote follows a deferral in September and is a resolution supporting the development rather than confirmation that planning permission has been formally issued.
Why Como Street has no affordable homes
The absence of affordable housing is particularly significant because the applicant is owned by the council and the land is in public ownership.
Reporting on the earlier officer assessment, Romford Today identified the London Plan’s 50% affordable housing threshold for public sector land.
The same report said the developer’s financial assessment and construction costs had been independently reviewed before officers accepted that no affordable homes could currently be provided.
That does not mean the scheme has a permanent exemption from affordable housing policy, since the proposed legal agreement includes mechanisms to revisit viability.
Early and late reviews can assess whether changes in costs or development values create scope for an increased contribution.
The practical distinction is between the affordable housing secured at the outset and an additional obligation which might arise later if the financial position improves.
Our guide to Section 106 agreements explains how obligations associated with planning permission can secure commitments beyond the development itself.
Parking, heritage and construction
The council’s announcement of the original application in August 2025 described a slightly smaller scheme and confirmed that building heights had been revised following community feedback.
At that time, Mercury Land Holdings director Christopher Hobbs said: “Working closely with local residents has proved to be invaluable in helping to shape our plans.”
According to The Havering Daily, objections at the latest meeting included the effect on a nearby listed building and the loss of public parking.
The newspaper reports that councillors extended the scope of construction-related conditions to protect adjoining properties, not solely those in residential use.
Planning agent Ben Thomas reportedly told the committee that more than £4 million would be provided towards infrastructure and services.
Romford Today’s November preview also identified proposals for additional controls on construction traffic, piling, servicing and wildlife surveys following September’s deferral.
The redevelopment would bring new commercial or community space alongside the homes, with landscaping and improvements along the River Rom.
Two separate developments in Romford
The committee also backed the separate Liberty shopping centre redevelopment, which could accommodate up to 900 homes through a phased scheme.
The combined potential of 1,038 dwellings brings the provision of services, public spaces and transport connections into focus across the wider town centre.
However, infrastructure contributions and affordable housing arrangements need to be considered separately for each development rather than treating them as a single planning application.
For the Como Street proposal, the final terms of the legal agreement and the wording of the decision notice will be important in establishing exactly what has been secured.
The application reference is P0897.25, and the latest formal planning status can be checked through Havering’s planning register.