An enforcement deadline of four months has been upheld for a vehicle repair business on land beside a pumping station in Uton, Devon.
Inspector Stephen Hawkins dismissed the appeal against Mid Devon District Council on 27 November 2026, while correcting the wording of its enforcement notice.
The notice requires the operator to cease vehicle repair, restoration and storage, remove the vehicles and associated tools, and demolish the workshop building.
Although the sole trader had reportedly relocated following compulsory purchase of the previous business premises, the Inspector rejected a request for eighteen months to comply.
Why the enforcement deadline was upheld
The council issued the enforcement notice on 17 February 2026 following an earlier unsuccessful planning appeal concerning the workshop and its use.
That earlier appeal decision, reference 3355988, was dismissed on 27 May 2025 because of the location of the development and concerns about flood risk.
The latest appeal was brought solely under ground (g) of section 174(2) of the Town and Country Planning Act 1990, concerning the compliance period.
It therefore did not reopen the question of whether planning permission ought to be granted for the building or business use.
The Inspector found no firm evidence of a significant shortage of suitable alternative premises that could be occupied within a reasonably short period.
Although some equipment and larger vehicles might be awkward to move, he considered that the operator’s experience in the motor trade would assist with relocation.
He also considered the demolition of the metal-framed building and removal of its concrete slab to be relatively straightforward work for a commercial contractor.
The four-month period allowed for unforeseen delays, including possible flooding, while enabling demolition to minimise disturbance to wildlife.
Time spent appealing can be relevant
The decision is particularly useful because the Inspector expressly considered the time that had already elapsed since the notice was issued.
He explained that the appeal delay had been affording the appellant substantially greater time in which to search for and secure suitable alternative premises
.
In this particular case, the challenge concerned only the time allowed, so the operator already knew that the substantive requirements would remain in force.
An appellant seeking a longer enforcement deadline should therefore consider what practical preparations can reasonably be made while the appeal is being determined.
Our guide to enforcement appeal grounds explains why evidence of contractor availability, relocation arrangements and a realistic programme matters under ground (g).
The Inspector considered that extending the period would prolong the breach without sufficient justification, and that eligibility to pay business rates was of little relevance.
The notice was corrected, not quashed
The original allegation referred to storage of motor vehicles for repair, whereas the requirements also covered vehicle repair and restoration.
After seeking the views of both parties, the Inspector corrected the allegation under section 176(1)(a) so that it more accurately reflected the required cessation of use.
He concluded that the wording could be corrected without injustice, because the operator could reasonably understand the alleged breach and the steps needed to comply.
The practical distinction is that a correction does not itself secure planning permission or alter the four-month period where the substantive appeal has failed.
The Planning Inspectorate case record identifies the enforcement appeal as reference 6006576, and the appeal decision is also available on AppealBase.
Quoted Planning Inspectorate material is Crown copyright under the Open Government Licence v3.0.