Further environmental evidence for the Horse Hill oil development near Horley in Surrey is reportedly going out to public consultation from 26 November 2026.
The proposals concern a long-term oil production project involving four additional hydrocarbon wells alongside the two existing wells and supporting infrastructure.
The latest consultation follows the Supreme Court’s decision in June 2024 to overturn the planning permission granted for the project in 2019.
Specialist publication DrillOrDrop reported on 25 November that seven revised documents had been submitted following requests for more information from Surrey County Council.
What has changed at Horse Hill?
The latest material concerns the environmental assessment of the development rather than a fresh decision to approve or refuse oil extraction at the site.
The original development description, set out in a public notice published earlier this year, includes processing and storage facilities, tanker loading arrangements and a water reinjection well.
That notice describes a 25-year period for the development, including the retention and extension of the existing wellsite and its vehicular access.
DrillOrDrop reports that the council sought clarification on matters including the climate assessment, water resources, landscape effects, flooding and biodiversity.
The new submissions reportedly include revised environmental statement material, a non-technical summary and updates to the landscape and ecological assessments.
The operator maintains that its revised assessment does not change its conclusion concerning the significance of the climate effects, according to the specialist report.
That remains the applicant’s position rather than an assessment adopted by the planning authority or a conclusion reached by its planning committee.
Why the Finch judgment matters
The legal background makes this consultation particularly relevant beyond Surrey, because the same site gave rise to a leading judgment on environmental impact assessment.
In R (Finch) v Surrey County Council and others [2024] UKSC 20, the Supreme Court considered the emissions resulting from the eventual combustion of the oil.
The majority concluded that those emissions were indirect effects of the extraction project that should have been assessed before the planning permission was granted.
The ruling did not impose a blanket prohibition on oil extraction, but the original decision could not stand on the environmental information before the council.
For practitioners, I would distinguish the requirement to assess an environmental effect from the subsequent judgment about its significance and the overall planning merits.
Landscape effects will also remain relevant, as explained in our guidance on landscape character assessment, alongside the other environmental matters raised in this case.
What happens next?
DrillOrDrop reports that Surrey County Council is seeking further representations specifically on the new information and that the consultation closes on 28 December 2026.
The specialist publication quotes the council as inviting “observations on the new information contained within these 7 documents”.
Anyone wishing to respond should check the county council’s planning register under reference SCC Ref 2018/0152 for the current documents and consultation arrangements.
The submission of more information does not mean the environmental issues have been resolved or that the council has accepted the applicant’s conclusions.
Once the consultation responses have been considered, the council will still need to reach a decision on the planning merits of the Horse Hill application.