Housing delivery costs have prompted calls to replace existing developer contributions with a single infrastructure levy, in a new report from housebuilder Pocket Living.
The report, covered by construction and housing trade publications on 26 November 2026, sets out nine ideas to improve the economics of British housebuilding.
Its comparison of a 38 square metre London flat puts the cost of delivery before land at £247,000 in 2026, against £174,000 in 2020.
The proposals include changes to planning contributions, public engagement and affordable homeownership, rather than a new government decision to abolish the existing charging system.
Why housing delivery costs have risen
The Build Again: Hope Again report attributes £16,000 of that £73,000 increase to planning and obligations, with construction and borrowing accounting for the remainder.
That comparison concerns the developer’s own example of a compact London home, rather than a representative calculation for every housebuilding project in England.
A further difficulty arises when homes remain unsold following completion, because finance costs can continue to accumulate while the developer waits to recover its investment.
The report’s foreword by Pocket chief executive Paul Rickard argues that the policy framework has not kept pace with changes in the industry.
Rickard told PBC Today that the industry needs a “fundamental rethink of the economics of housebuilding”.
These concerns sit alongside today’s official housing supply figures, which show that England added 203,690 net homes during 2025/26.
A different approach to developer contributions
Centre for London contributors Rob Anderson and Daniel Reast propose a charge calculated by floorspace, with rates established for different areas through Local Plans.
Their proposed system would direct money into separate infrastructure and affordable housing funds, with provision for exceptional development costs and incentives for additional affordable homes.
For developers, knowing the likely contribution before agreeing a land purchase could reduce uncertainty when preparing the initial financial appraisal of a scheme.
However, different sites within the same area can face very different costs for ground remediation, utility connections, drainage and highway works.
The detail of any exceptions would therefore matter, particularly for previously developed sites where unexpected remediation requirements could undermine an otherwise viable proposal.
Our guides to Section 106 agreements and the Community Infrastructure Levy (CIL) explain the separate mechanisms that developers currently need to consider.
Replacing financial contributions would also require careful consideration of how councils could secure necessary site-specific works and commitments that cannot simply be expressed as a charge.
Other proposals and what happens next
The National Federation of Builders’ contribution calls for clearer reporting of unspent developer funds and an automatic repayment mechanism after five years in specified circumstances.
Pocket Living separately suggests a discounted homeownership model under which eligible graduates could exchange part of their student debt for a government equity interest.
As Show House reports, the wider recommendations address the demand for homes as well as the costs of supplying them.
The report also discusses construction skills, factory-built homes and changes to public participation, reflecting its authors’ view that planning reform alone will not resolve delivery problems.
None of these suggestions alters an existing planning obligation or removes liability for CIL, and developers should continue to budget for the current requirements.
The practical test for any future reform is whether it makes housing delivery costs more predictable without leaving communities short of the infrastructure and affordable homes they need.

0 Comments