Padel court appeal fails despite no sequential test

Brackley farm diversification padel scheme fails at appeal on landscape grounds, although the Inspector finds two courts need no sequential test.

by | 20th November 2026 21:57 | Agriculture & EquestrianAppealsPlanning ApplicationPlanning Policy

A padel court appeal near Brackley has failed despite an Inspector deciding that two proposed indoor courts would not require a town centre sequential test. West Northamptonshire Council’s refusal was upheld on 20 November 2026 because the building would harm an open countryside setting.

The plan was to provide two padel courts within a new agricultural-style building at Hall Farm, Radstone. Appellant Will Brown promoted the scheme as a low impact farm diversification initiative, providing an alternative revenue stream for a holding fragmented by HS2 works.

The padel court appeal is a useful example of how a positive finding on one disputed planning test does not resolve the rest of the decision. The Inspector accepted that the proposal was not an intensive town centre use, but found that its prominent position and separation from the existing farm buildings were decisive.

Why the padel court appeal was dismissed

Inspector David Smith considered appeal 6012518 against the refusal of application 2026/0299/FULL. The site lies roughly 500 metres north of Brackley’s built-up edge, near agricultural buildings and land affected by the HS2 project. The development would include parking and an access route using an existing track.

Although the proposed building would use metal cladding familiar in farm settings, the Inspector found that it would sit in a visible gap rather than alongside the existing group of buildings. It would interrupt views into the surrounding countryside and lack established screening from the road. No detailed or indicative planting proposal had been put forward to demonstrate how it might be integrated into the landscape.

In the decision, Inspector Smith described how the building would “stand out starkly” because of its position and separation from other structures. That physical relationship, rather than an objection to padel as a sport, was central to the outcome. The conclusion was that the development would harm the area’s character and appearance and conflict with the relevant local design and countryside policies.

A small padel scheme did not trigger a sequential test

The more distinctive feature of this padel court appeal was its treatment of national town centre policy. The Inspector recognised that the National Planning Policy Framework includes more intensive sport and recreation uses among the activities potentially requiring a sequential test when proposed outside a centre. He nevertheless distinguished these two courts from facilities operating at a materially larger scale.

At most eight players could use the courts at one time. A typical game or coaching booking would last around 60 to 90 minutes, limiting the number of sessions and associated journeys. If the building opened for 12 hours a day, the Inspector expected a maximum of eight to ten bookings. He held that the scale and pattern of activity did not amount to a more intensive sport and recreation use.

He compared the proposal with other appeal decisions, including one involving seven courts and a café where a sequential test was necessary. Those decisions did not determine the different circumstances at Hall Farm. His conclusion was clear: “a sequential test is not required.” This is a factual, scale-sensitive assessment, not a blanket exemption for all padel centres.

Planning Geek’s guide to padel court planning permission explains the separate considerations that can apply to indoor and outdoor courts, including planning use, buildings, lighting, noise and location. The Brackley decision illustrates why the actual intensity of the proposed activity must be examined rather than inferred from the name of the sport.

Farm diversification did not outweigh landscape harm

The applicant presented the scheme as a response to pressures on farming. HS2 had fragmented the holding, while rising costs, changes to agricultural support and uncertainty over future payments placed additional pressure on profitability. The Inspector accepted the broad importance of farm diversification and the need to support rural businesses.

However, the padel court appeal lacked evidence explaining what this particular investment would contribute to the farm’s finances. The Inspector did not demand an exhaustive business appraisal. Rather, he considered that the consequences of granting or refusing permission, and the proposed building’s contribution to the holding, had not been sufficiently explained to justify the greatest weight for diversification benefits.

Some new part-time work and spending by visitors were potential benefits, but the local economic effects were not quantified. The recreational benefits carried more weight. Brackley had no padel courts, with alternative provision in Bicester and Northampton, and the Inspector acknowledged that a new facility could contribute to health and social interaction.

That did not make the location acceptable under policies supporting appropriate farm diversification and countryside recreation. Those policies also required a building to respect its landscape setting and relate sensibly to the established farm complex. On that point, the Inspector found the proposal wanting.

Transport and biodiversity were not the main obstacles

Some players could cycle from nearby homes, but the courts would also attract visitors from a wider area. Many were likely to drive, so the proposal would not clearly promote sustainable transport. The Inspector gave this adverse consideration limited weight because cycling remained feasible and the site was comparatively close to the town.

Ecological concerns had been addressed by revised information. The Inspector also recorded that the statutory biodiversity gain plan would need approval before development could begin and that proposed skylark mitigation on nearby arable land could be secured through a suitably framed condition. Those matters did not justify dismissing the padel court appeal.

What developers can take from the decision

The principal lesson is that a development can pass the sequential-test question yet still fail under countryside, design and locational policies. The scale of a sports venue matters, but so does where its building sits in relation to existing structures, views, access routes and the landscape. Agricultural styling alone cannot guarantee visual acceptability.

For landowners seeking a new commercial diversification use, evidence of the farm’s financial circumstances is only the starting point. The application needs to explain why the particular proposal, and that particular siting, are necessary and how its benefits would be delivered. Where opportunities exist to group development with farm buildings or strengthen landscape integration, those options deserve early attention.

The padel court appeal ended with the Inspector dismissing the scheme on 20 November 2026, despite accepting significant recreational benefits and finding no need for a sequential test. The full appeal decision is recorded under reference 6012518. It is also available on AppealBase.

0 Comments

Submit a Comment

Affected by this story, or spotted something we should check? Report an issue with this article

Planning news by email

Get the latest Planning Geek stories in one daily digest.

Finding Planning Geek useful?
Buy Ian a coffee to say thanks

Media enquiries

Journalist, broadcaster or producer? Need a quick comment on a planning story, policy change or decision?

Request a comment →

YouTube

Planning Geek on YouTube

Watch Ian explain permitted development, use classes, planning applications and current planning changes.

Watch on YouTube

Latest planning news