North Northamptonshire Council has decided to pursue a solar farm challenge against the government’s approval of the 500MW Green Hill development, according to reports on 23 November.
The project extends across roughly 1,200 hectares of land in Northamptonshire and Milton Keynes, with solar arrays, battery storage and associated infrastructure.
The authority says its proposed judicial review will focus on how the impact on local heritage was considered when development consent was granted on 8 October.
The council’s decision to pursue legal action is a new development, although the filing date, claim number and any decision granting permission to proceed have not been confirmed.
Solar farm challenge focuses on heritage
The Northamptonshire Telegraph reported that the council had considered its legal position and decided to seek judicial review, citing a statement from the authority.
The council’s leader, Martin Griffiths, said he was “appalled by the industrialisation of our countryside” and the impact the development could have on rural communities.
His concerns include the effect of the development on villages including Mears Ashby, Grendon and Easton Maudit, where the landscape would change during the project’s operation.
Council representatives have also expressed a preference for installing solar panels on existing commercial buildings and other developed sites rather than agricultural land.
Those wider objections should be distinguished from the stated focus of the proposed legal challenge, which concerns the consideration of heritage impacts.
In response to the announcement, developer Island Green Power said it would participate in the process, according to BBC reporting carried by Yahoo.
Development consent remains in place
As covered in our October report on Green Hill Solar Farm, the Secretary of State approved the scheme following examination under the nationally significant infrastructure planning regime.
The Green Hill Solar Farm Order 2026 was made on 8 October and came into force on 30 October.
The development involves a number of separate parcels, with associated electricity infrastructure linking the solar arrays and storage facilities to the grid at Grendon.
The developer expects the generating capacity to provide electricity equivalent to the annual consumption of around 200,000 homes, according to the reported project information.
The Northampton Chronicle and Echo reports that construction could begin in 2027, with a grid connection planned for 2029.
Neither the council’s announcement nor the reported intention to challenge the order amounts to a court decision setting aside the development consent.
What a judicial review can consider
Section 118 of the Planning Act 2008 requires challenges to a development consent order to be brought by judicial review within the specified six-week filing period.
That period runs from the day after publication of the order or, if later, publication of the statement of reasons for making it.
Reporting about the project identified 19 November as the relevant deadline, but the date on which the council filed any claim has not been independently established.
A judicial review is concerned with whether a decision was taken lawfully, rather than inviting a judge to determine the planning merits of the solar development afresh.
Our guide to challenged planning decisions explains why court proceedings must be distinguished from the original planning decision-making process.
The next milestone in the solar farm challenge will be confirmation of the court proceedings and whether the High Court grants permission for the claim to proceed.