Clydesmill grid upgrade opens Scottish consultation

Scottish grid upgrade plans enter public consultation, with six cable options and a future section 37 application yet to be submitted.

Public consultation on the Clydesmill grid upgrade opened on 2 November 2026, giving communities between Cambuslang and Strathaven until 1 December to comment on proposed changes to a 10.4-kilometre electricity transmission corridor. SP Energy Networks is proposing new equipment, an underground cable and changes to existing overhead lines in South Lanarkshire. This is an initial consultation, not a planning application or an approval to build.

The Clydesmill grid upgrade would enable the eastern circuit of the existing double-circuit overhead line to operate at 400 kilovolts, while the western circuit would continue at 275 kilovolts. The company proposes new towers at Clydesmill and Strathaven substations, an extension at Strathaven substation and a new underground 275-kilovolt connection to the Malcolmwood compound. Several cable routes remain under consideration.

This matters to local landowners and to Scottish planning practice because a route that already carries electricity can still require separate consents for new works. SP Energy Networks anticipates applying to Scottish Ministers under section 37 of the Electricity Act 1989, with deemed planning permission requested under section 57(2) of the Town and Country Planning (Scotland) Act 1997. Ministers have not been asked to determine the proposal yet.

What the Clydesmill grid upgrade would change

The existing overhead line runs between Clydesmill substation at Cambuslang and Strathaven substation near Hamilton. SP Energy Networks proposes refurbishing and replacing conductors on a stretch measuring approximately 10.4 kilometres, with tower and foundation strengthening where required. The company says keeping existing infrastructure in use should reduce the amount of new construction, although there will still be substantial work at the substations and along the corridor.

The voltage arrangement in the Clydesmill grid upgrade is not a proposal to turn both circuits into 400-kilovolt lines. The company’s published Clydesmill to Strathaven project information says the eastern circuit would be uprated, while the western circuit would remain at 275 kilovolts to support supplies to East Kilbride. It is an important technical distinction: the new structures and connections are intended to support a split-voltage operation, rather than simply replacing every part of the existing line.

Further elements include a new 275-kilovolt underground cable between Strathaven substation and Malcolmwood, a new bay at the existing Strathaven compound and new towers at the two substations to connect the circuits. Potential temporary compounds, site access routes, hardstanding and vegetation clearance are also identified. Those temporary arrangements can have real environmental and transport consequences, even where the permanent overhead corridor already exists.

Six underground cable routes and an unsettled alignment

SP Energy Networks has identified six indicative underground cable options. It calls Option 5 its current preferred route but expressly states that the alignment remains open to change following technical work and consultation. The company says the underground cable route has not been finalised. People with land interests should therefore review the route information now rather than assume that a preferred line has already become a fixed statutory boundary.

The Clydesmill grid upgrade is also relevant to residents who are not directly beneath an overhead conductor. Underground cabling can involve excavation, temporary access, soil storage, restoration and possible crossing arrangements. The precise corridor, extent and construction methods will be matters for subsequent design and environmental assessment. None of the published indicative options should be described as a compulsory purchase decision or a completed legal agreement.

The developer says it will seek to use existing access arrangements where practical and contact affected owners and occupiers. It expects to negotiate voluntary arrangements for the eventual cable route. That is not a statement that every necessary right has already been obtained, nor does the launch of consultation itself give contractors a general entitlement to enter neighbouring land.

What consent would be needed in Scotland?

The present consultation is the first round of engagement with affected communities. After taking account of comments, SP Energy Networks says it intends to refine the Clydesmill grid upgrade, undertake environmental assessment and hold a second public consultation. It then expects to apply under section 37 of the Electricity Act 1989 and seek deemed planning permission from Scottish Ministers under the Scottish planning legislation. That is a different legal process from an ordinary local council planning application.

The company says improvements to existing towers and reconductoring have already been consented and are not being re-applied for as part of the new application. Nevertheless, it intends to include relevant effects of those works in the Environmental Impact Assessment accompanying the future submission. This matters because assessing one consent application in isolation can obscure the effects of connected work on the same transmission corridor.

An application has not yet been submitted for the remaining proposed works, and no decision on those future permissions has been made. The distinction between engagement and statutory determination is central to Planning Geek’s introduction to planning in Scotland. Interested parties will have a later formal opportunity to make representations to the Energy Consents Unit after an application is lodged.

Consultation dates and how to respond

The consultation opened on Monday 2 November and closes on Tuesday 1 December 2026. A public drop-in was arranged at Halfway Community Hub in Cambuslang on 2 November; another was arranged for Hillhouse and Earnock Community Centre in Hamilton from 3pm to 7pm on 3 November. The developer’s project webpage provides maps, consultation material and a feedback form, with email and postal alternatives for people unable to attend.

SP Energy Networks is asking for comments on the initial proposals, particularly where the route and local construction arrangements may affect communities. A useful response would identify the precise property or environmental feature, the likely effect and any practical alternative. Questions about access, agriculture, woodland, watercourses, public paths, construction traffic and substation activity are more actionable than a general statement that electricity infrastructure is undesirable.

The developer makes clear that comments at this stage are not formal representations to the Scottish Ministers. Formal statutory consultation is expected after the project reaches the application stage. Anyone making a submission now should retain a copy and follow later notices rather than assume an initial response will automatically be treated as an objection to a future consent application.

When could the Clydesmill grid upgrade be built?

SP Energy Networks currently anticipates submitting its section 37 application in early 2029. Subject to approvals, its indicative construction programme runs from 2030 to 2032. Those dates could change as engineering and environmental work progresses. It has not published a final project cost, so any headline claiming a fixed financial value or imminent start to construction would go beyond the information available.

The company says the investment responds to growing electricity demand and a need to move renewable energy through the network more effectively. That national energy rationale is relevant, but the Scottish Ministers would still need to consider the submitted environmental evidence and representations when the application is eventually made. The proposed voltage increase does not decide the merits of a particular cable alignment or construction access route.

The immediate news in the Clydesmill grid upgrade is therefore modest but real: the first public consultation is open, there is a month to respond, and the route options and eventual application have not been settled. For affected owners and communities the sensible next step is to examine the published plans now, while recognising that the formal consent process lies further ahead.

0 Comments

Submit a Comment

Affected by this story, or spotted something we should check? Report an issue with this article

Planning news by email

Get the latest Planning Geek stories in one daily digest.

Finding Planning Geek useful?
Buy Ian a coffee to say thanks

Media enquiries

Journalist, broadcaster or producer? Need a quick comment on a planning story, policy change or decision?

Request a comment →

YouTube

Planning Geek on YouTube

Watch Ian explain permitted development, use classes, planning applications and current planning changes.

Watch on YouTube

Latest planning news