Scottish housing tender prices fall in provisional figures

The Scottish figures cover April to June 2026, with rising underlying costs and an eight-project sample limiting the headline fall.

by | 13th October 2026 07:31 | Scotland

Scottish housing tender prices fell by a provisional 2.1% between January to March and April to June 2026, according to a Scottish Government report published on 12th October 2026. Prices accepted for social housing construction nevertheless remained 1.2% higher than a year earlier.

The September quarterly briefing covers Scotland’s social housing schemes, rather than every building project or the prices people pay to buy a home. Its latest result is based on eight projects and may change as further tenders are added. For councils, housing providers and communities awaiting new homes, it offers a qualified indication of construction pricing.

I would treat this as a useful budgeting signal, with a sizeable caution attached. A fall in one small quarterly sample does not establish that your next scheme will be cheaper, or that rising labour and material costs have disappeared. The report actually records increases in those underlying costs.

What the housing tender prices report measures

The official publication sets out the Scottish Social Housing Tender Price Index. A tender is a contractor’s offer to undertake work for a stated price. This index uses accepted construction tenders for affordable housing, with adjustments intended to make different schemes more comparable.

The full five-page quarterly briefing was prepared by the Building Cost Information Service, known as BCIS, for the Scottish Government’s More Homes Division. It compares schemes with cost models for different dwelling types, sizes and occupancy, then adjusts for design, specification, location and project size.

The resulting housing tender prices index is a guide to movement across the sampled social housing schemes. It is not a quotation for an individual development. A difficult site, unusual design or different contract package still needs its own assessment, even where the broad national direction appears favourable.

The September label does not mean September building costs

The publication date and the period measured are different. Although this is the September 2026 briefing, the latest construction-tender data relate to April to June 2026. That is the first quarter of the 2026/27 financial year and the second quarter of the calendar year.

The latest housing tender prices index stands at 422, compared with 431 for January to March 2026 and 417 for April to June 2025. The published quarterly decrease is 2.1%, while the annual comparison gives an increase of 1.2%. Those changes describe two different comparisons and can both be true.

I would keep all three dates visible when using the figures: the quarter being measured, the briefing’s September label and its 12th October publication. Calling these current October construction costs would give readers the wrong impression about how recent the underlying project evidence is.

Eight projects make the latest result provisional

The Government explicitly says that the latest index “will be subject to revision as more projects are indexed”. That warning belongs alongside the headline fall. The eight projects counted for April to June contrast with 21 for January to March, whose index also remains provisional.

Earlier housing tender prices have already moved as the evidence has developed. The October to December 2025 result is now firm, based on 23 projects, and shows a 2.1% quarterly increase and an 8.0% annual increase. The current release therefore contains revised earlier evidence as well as the newest quarter.

The report explains that the quarterly calculation averages adjusted project indices and smooths the result to account for variation in sample sizes. These methods improve comparability, but the published warning still matters. We should not turn a provisional fall into a confident forecast of the next tender round.

Underlying construction costs continued to rise

Alongside housing tender prices, the briefing reports a separate measure of labour, materials and plant costs. The BCIS General Building Cost Index increased by 1.8% over the quarter and 4.2% over the year to April to June 2026. Consumer price inflation over that year was 2.7%.

Tender prices and underlying costs measure different things. An accepted bid is the price offered for a construction contract, whereas the cost measure tracks inputs used in building. A fall in the former alongside a rise in the latter does not, by itself, tell us precisely why contractors priced the sampled schemes as they did.

There is no evidence in this briefing to attribute the quarterly fall to a specific planning reform, stronger competition or improved productivity. I would avoid attaching any of those explanations to the figures without further evidence. The useful finding is the divergence between the two measures, rather than an invented cause.

Regional figures use a longer period

The publication also contains location indices for Scottish areas. These compare adjusted local construction prices with the Scottish mean, set at 100, and use evidence across 15 quarters. They are provisional and should not be confused with a single quarter’s regional price change.

For example, the table records 114 for the City of Glasgow, 101 for the City of Edinburgh and 92 for Highland. Angus, Perth and Kinross records 122, while Dundee City records 89. Those are index levels against the stated benchmark, not percentage increases or decreases over the latest quarter.

The regional housing tender prices evidence also has differing sample sizes. Glasgow’s entry uses ten projects, Edinburgh’s 14 and Dundee’s five. Entries with four projects or fewer are omitted. Comparing locations sensibly therefore means checking both the calculation period and the amount of evidence behind each value.

What housing providers and landowners can use it for

The report says the index is used to update the indicative cost calculation within the Housing Tender Return. That return is part of the Scottish Government’s grant-funding process for relevant affordable housing projects. The index therefore has a practical role beyond providing a headline about construction inflation.

The Government’s Housing Tender Return guidance explains that grant applicants must complete and upload a current return. If you are involved in a funded scheme, check the current published requirements and project costs together rather than assuming a national index settles the funding position.

For landowners discussing an affordable housing proposal, housing tender prices can inform the conversation about delivery costs. They cannot establish a site’s viability on their own. Land terms, site preparation, design requirements and the actual procurement outcome need to be understood separately.

Nor does this statistical release grant planning permission or change development-plan policy. A proposed scheme still needs the relevant planning assessment. Our Scotland section brings together Scottish planning coverage, where the legal and policy context differs from England.

My practical reading is to retain the provisional figure as one piece of evidence, then revisit it when the next release arrives. The latest housing tender prices point down over one quarter, but underlying costs point up and the sample remains small. That combination calls for careful project budgeting rather than assuming the pressure has ended.

0 Comments

Submit a Comment

Affected by this story, or spotted something we should check? Report an issue with this article

Planning news by email

Get the latest Planning Geek stories in one daily digest.

Finding Planning Geek useful?
Buy Ian a coffee to say thanks

Media enquiries

Journalist, broadcaster or producer? Need a quick comment on a planning story, policy change or decision?

Request a comment →

YouTube

Planning Geek on YouTube

Watch Ian explain permitted development, use classes, planning applications and current planning changes.

Watch on YouTube

Latest planning news