Skip to content
Planning Geek logo

Planning consultancyBacked by the UK's leading planning resource

PLANNING NEWS

Kempsey housing appeal cuts supply to 4.5 years

An Inspector allows up to 99 homes at Kempsey after removing 1,400 anticipated dwellings from South Worcestershire’s five-year housing land supply.

by | 24th November 2026 07:48 | AppealsLocal PlanPlanning ApplicationPlanning PolicySection 106

A Kempsey housing appeal has granted outline planning permission for up to 99 homes at Bannut Hill in Worcestershire despite development plan conflict.

Inspector AJ Sutton allowed the appeal on 23 November 2026 after finding that South Worcestershire could demonstrate only around 4.5 years of housing land supply.

The Inspector excluded 1,400 homes on two strategic sites from the five-year calculation, just eight months after adoption of the South Worcestershire Development Plan Review.

The scheme involves demolition of an existing dwelling, new vehicular access, green infrastructure and drainage, with a legal agreement securing 40% affordable housing.

Why the Kempsey housing appeal changes the supply picture

Malvern Hills District Council had refused application M/25/00323/OUT in December 2025, before the replacement development plan was adopted.

The council chose not to defend its original refusal reasons, but the Inspector still assessed the location, landscape effects and safety of construction access.

For me, the Kempsey housing appeal turns on when homes at Worcestershire Parkway New Settlement could be built, because the council had counted 900 within five years.

The Inspector identified outstanding outline applications, unresolved infrastructure requirements and insufficient evidence on the timing and rates of delivery at the strategic allocation.

The decision concluded that there was “no realistic prospect that the projected number of dwellings can be delivered within the 5-year period”.

A further 500 anticipated dwellings were removed from the supply at the Mitton strategic sites, where reserved matters and infrastructure arrangements remained outstanding.

The Inspector noted that the recent plan examination had considered a 10% buffer, rather than the 20% buffer now required for this assessment.

Using an annual housing requirement of 1,178 homes and the higher buffer, the Inspector identified a five-year target of 7,070 dwellings.

The two adjustments were sufficient to leave a significant shortfall even if the council’s evidence on other disputed sites were accepted.

A recently adopted Local Plan was not decisive

The Inspector found that Kempsey’s neighbourhood plan restriction on development outside the village boundary was materially inconsistent with the new national policy for development outside settlements.

The appeal site immediately adjoins the built-up area, and the Inspector found that it was physically well related to the village.

Concerns about construction traffic remained, but the Inspector considered that acceptable arrangements could be secured through planning conditions.

Infrastructure contributions and other measures secured through the legal agreement supported the conclusion that the development could be accommodated at this scale.

The decision does not establish a permanent housing land supply figure, but illustrates the importance of up-to-date evidence about deliverability after Local Plan examination.

Affordable homes and delivery commitments

The agreement provides for 40% affordable housing, split between 70% social rented accommodation and 30% shared ownership, alongside self-build provision.

The Inspector gave substantial weight to the housing benefits, noting the strong evidence that this less complex site could deliver within five years.

The decision also acknowledged landscape harm and a very limited adverse effect on the significance of a nearby heritage asset.

If your application depends on the supply figure, check what permissions, funding and infrastructure the council can show for its largest sites.

The council’s application register lists the original planning refusal and the subsequent appeal outcome under reference 6008572.

The appeal decision is also available on AppealBase.

The official appeal register identifies the case, with quoted Planning Inspectorate decision material reproduced under the Open Government Licence v3.0.

0 Comments

Submit a Comment

Affected by this story, or spotted something we should check? Report an issue with this article

Planning news by email

Get the latest Planning Geek stories in one daily digest.

Finding Planning Geek useful?
Buy Ian a coffee to say thanks

Media enquiries

Journalist, broadcaster or producer? Need a quick comment on a planning story, policy change or decision?

Request a comment →

YouTube

Planning Geek on YouTube

Watch Ian explain permitted development, use classes, planning applications and current planning changes.

Watch on YouTube

Latest planning news