The Scottish fire safety review has found strong support for revising building standards, according to consultation analysis published by the Scottish Government on 26 November 2026.
The analysis covers 57 respondents, including 45 organisations, and examines proposed changes to technical guidance, professional accountability and the verification of building work.
Among the 53 respondents who answered the relevant question, 98% supported reviewing existing fire safety topics in Scotland’s domestic and non-domestic technical handbooks.
The publication is an evidence-gathering milestone following the Grenfell Tower Inquiry, rather than the introduction of new mandatory requirements for developers or building owners.
What the Scottish fire safety review found
The detailed analysis of standards and guidance shows particular interest in external fire spread, the performance of cladding systems and the treatment of cavities.
Respondents also wanted greater clarity about the evidence necessary to establish compliance when designers propose complex external wall systems or alternative technical solutions.
The findings reflect concern about differences in how requirements are interpreted and applied, with some respondents seeking clearer explanations and practical examples.
The report also identifies emerging technologies, including lithium-ion batteries and solar photovoltaic systems, as topics that respondents believe warrant further attention.
Evacuation and the design of buildings
A separate chapter on means of escape records that 66% of those answering considered the guidance for vulnerable and disabled people neither effective nor up to date.
Respondents highlighted the challenges of assisted evacuation in multi-storey residential buildings, with suggestions covering evacuation lifts, refuge spaces and personal emergency evacuation plans.
For architects and developers, these issues are relevant to early design work because circulation space, vertical access and building layout can be difficult to alter later.
The Scottish fire safety findings do not establish that any particular building is unsafe or that the suggested technical solutions are already mandatory.
Potential changes before a building warrant
The consultation also examined the developing Compliance Plan Approach, including proposals for a more formal role for the person responsible for managing compliance.
According to the pre-warrant findings, 80% of those answering supported only registering a high-risk building warrant after a Compliance Plan in Principle had been issued.
A proposed 12-week period for submitting that preliminary plan also received majority support, although the report records differing views about the appropriate timetable.
The legislation chapter records that 92% of respondents answering the relevant question supported legislation to give full effect to the approach for high-risk buildings.
These proposals matter commercially because any future requirement for an earlier compliance submission could influence the sequence of design appointments, technical work and project approvals.
What happens next?
The original call for evidence ran from January to April 2026 and described the exercise as a “key first step” in the technical review.
At that stage the Scottish Government said its intention was to confirm and implement any regulatory changes by 2030, rather than commit to immediate amendments.
Planning permission and building standards approval remain distinct processes, and the publication of consultation findings should not be mistaken for a change to either consent regime.
Our guide to building regulations approval in England explains that distinction in the English context, although Scotland has its own building standards system.
Anyone preparing a substantial Scottish development should continue to work to the applicable requirements while keeping an eye on the emerging proposals as design decisions are made.