The Liverpool Waters masterplan is due to return to Liverpool City Council’s planning committee next week, with Peel Waters seeking to reduce the overall housing figure from 9,000 to 7,111 homes. Property publication Place North West reported the latest figures on 17 November 2026. Councillors are being asked to consider revisions to an established docklands regeneration scheme, not a fresh permission for 7,111 new flats.
The reduction is not confined to homes. According to the report, planned office space falls from approximately 3.3 million to 1.2 million square feet, while retail, restaurant and bar space drops from 880,000 to 277,000 square feet. It is a substantial reshaping of the mix and scale of one of Liverpool’s largest long-term development projects.
The Liverpool Waters masterplan also provides an interesting planning-law question. The underlying application, 24F/1916, was submitted in July 2024 under section 73 of the Town and Country Planning Act 1990 to vary numerous conditions and schedules attached to the original outline consent. The new news event is its reported move towards committee consideration in November 2026, not an application first submitted this week.
Liverpool Waters masterplan: 1,889 fewer homes
Place North West says the 150-acre waterfront masterplan would now accommodate 7,111 homes against 9,000 in the earlier vision. That is a reduction of 1,889 dwellings in the overall planned total, rather than a claim that 1,889 consented homes are being demolished or that 7,111 units would all be additional to what has already been built.
The distinction matters. The specialist report says just under 1,300 homes have already been delivered under separate permissions since the outline development was authorised in 2013. A revised masterplan should therefore be read as the intended total scale of development across the regeneration area, including its existing progress, rather than as an overnight construction programme.
A major reason for the smaller residential allocation is the arrival of Everton’s Hill Dickinson Stadium. The stadium occupies part of the northern docklands previously identified for housing and changes the pattern of movement, activity and development around the site. It is an important example of how a multi-decade outline scheme can evolve as major surrounding projects are delivered.
The Liverpool Waters masterplan covers the historic northern docks along the River Mersey, including established Princes Dock developments and the emerging Central Docks neighbourhood. The reduction across the whole area does not mean that every consented plot or the current Central Docks infrastructure works are being cancelled. Individual reserved matters, permissions and construction phases must still be checked on their own terms.
Office and retail floorspace cut sharply
The proposed commercial changes are at least as significant as the housing adjustment. The office allowance would fall by approximately 2.1 million square feet, from 3.3 million to 1.2 million. The allowance for shops, restaurants and bars would decline by about 603,000 square feet, leaving 277,000. Place North West reports that the overall amount of built floorspace would fall by around eight million square feet.
Those are substantial reductions in capacity for future development, not evidence that occupied offices or shops are to close. The revised vision appears to reflect the modern demand for commercial property, the cost of major construction and how Liverpool’s other regeneration districts might serve different business markets.
The report says Peel wants to avoid putting its revised commercial offer into unnecessary competition with the emerging Ten Streets district. It also records that allocations for hotels, education, health, leisure, cultural attractions and similar uses would remain broadly unchanged. That is a more varied picture than simply describing the revised Liverpool Waters masterplan as a cut to housing.
In the design and access statement quoted by Place North West, the applicant says: The world has changed.
The statement refers to the city’s climate emergency, the pandemic and war in Europe as factors that have altered priorities. Those arguments explain the applicant’s proposed change of direction, but they do not settle whether the latest planning amendments meet the requirements for a further approval.
Why the Section 73 route matters
A Council for British Archaeology casework record identifies application 24F/1916 as a section 73 application to vary a lengthy list of conditions and Schedules 1 to 7 attached to the original outline planning permission, reference 10O/2424. The record gives 29 July 2024 as its received date. Liverpool City Council’s own online application-search service can be used to check the reference and any subsequent formal decision.
Section 73 is an application route for development without complying with conditions on an existing permission. It is not an automatic authorisation to replace every part of an approved development. The crucial documents are the original operative description of development, the conditions and approved parameters, and the exact terms sought in the revised application.
That is especially important for the Liverpool Waters masterplan, where alterations to the distribution and amount of uses are substantial. The size of a change alone does not answer whether a condition-variation route is legally available. The practical question is whether the proposal can be expressed through amended conditions consistently with the description of development, alongside the necessary assessments and procedures.
Our guide to section 73 applications explains the distinction between modifying conditions and changing a permission’s operative description. The current committee outcome and precise revised conditions have not yet been verified, so it would be premature to conclude that Liverpool has granted a replacement outline permission or approved each future building phase.
What is already happening at Central Docks?
The wider scheme is far from a blank site. Peel Waters said in an update published on 11 November that infrastructure work at Central Docks had made substantial progress in its first year, with work on utilities, drainage, routes, new bridge foundations and a planned public park. That is an existing construction programme within the broader regeneration area, not evidence that the latest section 73 proposal has been determined.
According to Peel, the Central Docks infrastructure project involves £81.1 million of works, supported by approximately £55.2 million from Homes England and £25.9 million from Peel Waters. The infrastructure is intended to support around 2,350 homes and mixed-use development over time. The new Liverpool Waters masterplan figures need to be understood alongside those already funded and progressing works.
This also matters commercially. Large outline permissions and masterplans provide a framework, but the delivery of individual residential blocks depends on access, servicing, utilities, investment partners, detailed approvals and market conditions. An amended masterplan may alter those future expectations without undoing infrastructure that is already under way.
Heritage, public space and Liverpool’s waterfront
Liverpool Waters occupies a prominent stretch of historic docklands. Peel’s original July 2024 announcement presented the revision as a move towards more public space, accessibility, sustainability and a more diverse housing offer, while retaining the historic dock setting as a central part of its identity. The developer’s development director, Chris Capes, described the updated vision at that time as a response to public engagement and changing priorities.
Those ambitions are relevant planning considerations, but they should not be confused with conditions already imposed by a formal decision. The eventual committee papers will be important for identifying what heritage, transport, ecology, phasing and public-realm safeguards members are actually being asked to approve. They will also show whether the proposed distribution of homes and other uses is consistent with the environmental assessment and the existing outline framework.
The Liverpool Waters masterplan is therefore not merely a matter of headline dwelling numbers. Reducing commercial floorspace and concentrating new buildings differently can change public transport demand, active travel routes, the setting of heritage assets, infrastructure funding assumptions and the relationship between residential neighbourhoods and destinations such as the football stadium.
What councillors will decide next
Place North West reports that the revised proposals will be discussed by Liverpool City Council’s planning committee next week. At the time of writing on 17 November 2026, this is a forthcoming consideration. The report does not establish that permission has been issued, that all proposed conditions have been approved or that any associated legal obligations have been completed.
The application reference is 24F/1916. The official Liverpool planning search provides the route to the live register, while Place North West’s 17 November report sets out the newly publicised scale changes. Peel’s original July 2024 announcement and its November 2026 construction update provide additional context.
The key next step for the Liverpool Waters masterplan is a verified committee resolution and the wording of any subsequent formal decision. For practitioners, this is a useful example of how long-running outline consents, condition variations and individual reserved matters must be kept distinct, especially where a developer substantially revises its programme over more than a decade.